Projects · 4 October 2016

Pedemontana Veneta: two PALADEX DN 2000 pipelines beneath the expressway

The spiral-wound steel-reinforced high-density polyethylene pipes pass beneath the route of the Pedemontana Veneta toll expressway to divert the Seriola and Brugnola irrigation channels.

Installation of two PALADEX DN 2000 pipelines beneath the Pedemontana Veneta

The works

The scheme comprises two reinforced concrete structures: an inlet structure controlled by two manual sluice gates, and an outlet structure, a flow-splitting structure with two sluice gates to regulate flows into the irrigation channels. Between them, two parallel spiral-wound pipelines with an internal diameter of 2000 mm, each around 100 m long, have been laid to act as an inverted siphon.

Upstream, the new alignment connects to the Roggia Breganze via an earth channel; downstream it divides into the Roggia Brugnola to the west and the Roggia Seriola to the east.

Installation

The first phase delivered the inlet structure, the inverted siphon and around 80 m of the two pipelines beneath the new road; the southern section is completed once traffic has been diverted. After excavation to design level, the pipelines were laid, welded and covered with sand, with a surface protection of lean concrete and double-mesh reinforcement.

On site, the pipes proved easy to install and handle, with greater alignment accuracy and much shorter assembly times. Hydraulically, the smooth internal wall and the absence of sockets reduce roughness and deposits.

Full article (PDF)

Excavation for laying the pipelines
Pedemontana Veneta: the excavation at design level before laying
Laying a PALADEX DN 2000 pipeline
Pedemontana Veneta: laying a PALADEX DN 2000 pipeline, class SN 16
The two PALADEX DN 2000 pipelines side by side
Pedemontana Veneta: the two PALADEX DN 2000 pipelines side by side, operating as an inverted siphon
Internal welding with a hand-held extruder
Pedemontana Veneta: internal welding with a hand-held extruder, watertight above 2 bar
Pedemontana Veneta construction site with PALADEX pipelines
Pedemontana Veneta: the construction site beneath the expressway alignment

Source: Servizi a Rete, September–October 2016